Restoring Coldwater Fish Habitat

Monora Park is a 17-hectare natural park owned by CVC and managed by the Town of Mono. Within Monora Park, Monora Creek was dammed in 1965 to create a pond suitable for recreation including swimming and fishing. Over time, as the pond has filled with silt, it no longer provides a place for swimming and fishing, although it remains a local landmark. Today, the park acts as an important greenspace for residents with 18 kilometres of walking, biking and cross-country ski trails, a picnic shelter, gazebo, open playing field, and Monora Pavilion – a venue for public and private events including weddings and conferences.

The Dam Structure

Begining in May 2022, we are lowering water levels in the pond in preparation for the eventual removal of the pond and dam, which has reached its end of life. This work will restore healthy habitat in Monora Creek and the surrounding wetlands.

The dam consists of an earth embankment (or berm) to hold back water which creates the pond and a ‘morning glory’ style spillway structure that regulates the water level. The integrity and structure of the aging dam has been in decline and is posing an increasing safety risk. A dam safety review completed in 2016 assessed the dam to be in poor to fair condition. The age and condition of the dam requires mitigative action and will need to be repaired or removed as the risk and liability of the dam failing increases over time.

We have evaluated different options for the Monora dam and associated pond, taking into consideration the goals of improving the natural environment of Monora Creek as well as safety, social, recreational and economic values.

The Restoration Process

There are several stages to restoring coldwater fish habitat in Monora Creek.

Set Objectives

Objectives for the project are:

  • Remove the risk to public safety and liability associated with the deteriorating dam
  • Remove the environmental impacts of the dam including improving stream temperature in coldwater fish habitat and removing the barrier to fish passage for sensitive brook trout population
  • Restore stream and wetland habitat in pond basin
  • Maintain and enhance trail connectivity for recreational purposes

Evaluate Mitigation Options

We evaluated four mitigation options using criteria to meet project objectives.

Option 1: Restore Monora Creek with wetlands – complete dam removal

  • Removes entire berm and spillway
  • Improves Monora Creek water temperature by removing warmwater pond
  • Restores fish passage by reconnecting upstream and downstream
  • Maintains wetland habitat

Option 2: Restore Monora Creek with wetlands – partial dam removal

  • Removes portions of berm only and entire control structure
  • Improves Monora Creek water temperature by removing warmwater pond
  • Restores fish passage by reconnecting upstream and downstream
  • Maintains wetland habitat

Option 3: Construct an artificial stream around the pond – rebuild dam

  • Rebuild dam
  • Restores fish passage by reconnecting upstream and downstream
  • Continued and sustained harm to environment
  • Continued long term liability and ongoing life cycle costs
  • Costly

Option 4: Rebuild dam

  • Continued and sustained harm to environment
  • Continued long term liability and ongoing life cycle costs
  • Costly

Preferred Mitigation Option:

Options one and two that would remove all or part of the dam and berm and restore the stream and wetland habitat ranked very closely in the assessment. The permitting and detailed design process will inform how much regrading will be required to construct an appropriately sized channel and stream crossing.

The preferred option will move into detailed design and permitting in consultation with provincial agencies, the public and stakeholders. Input received will help refine the final design that proceeds to construction.

The project’s construction is scheduled to be completed in 2023, June 15 to September 30.

Frequently Asked Questions

As the dam was built in 1965, it’s now at the end of its life cycle.

The dam does not meet current dam safety requirements. To maintain a pond would require significant cost and additional environmental assessment. We did evaluate options for keeping the pond (i.e., bypass channel) but maintaining a pond would cause continued harm to Monora Creek and the sensitive brook trout community that is at risk. Some of the pond wetland functions such as the marsh habitat will be incorporated into the design.

The benefits of removing the dam include contributing to CVC’s and the Town of Mono’s environmental and climate change goals, improving habitat and making the water cooler for sensitive and disappearing book trout. Removing the dam will also remove a barrier to fish movement by connecting Monora Creek upstream and downstream of the dam. Additionally, it will eliminate the safety risk and liability surrounding the aging structure.

Unfortunately, there will be some disruption to park access at this location during construction. We are hopeful that construction can be completed in less than three months. We are working with the Town of Mono staff to minimize construction disruptions. We do anticipate that trail access will be available at existing alternate access locations.

Impacts to fish and wildlife are minimized by the use of best management practices such as construction timing windows, isolating areas of disturbance from the construction and conducting fish and wildlife rescues as well as the implementation of sediment and erosion control measures.

We have collected extensive baseline data about the plants and animals using Monora Pond to incorporate these considerations into the detailed design and construction planning. The habitat that we restore will continue to provide habitat for the plants and animals that currently reside there. The detailed design will include provisions to maintain marsh habitat and improve stream habitat.  Other wildlife may migrate upstream or downstream to neighbouring open water habitat (e.g., Island Lake).

There is a provincial exemption from the Ministry of the Environment Climate Change and Parks under Ontario Regulation 334 to decommission dams built prior to the Environmental Assessment Act coming into effect in 1976. Monora dam was built in 1965 making it eligible for this exemption for decommissioning.

Monora dam was also built for recreational purposes and does not serve a flooding or erosion control function. The fish and wildlife management component of the project also meets exemption criteria for decommissioning under the Conservation Ontario Class Environmental Assessment process. CVC has adopted an EA like process in its feasibility study to assess a variety of options for its mitigation.

Rebuilding the dam requires an EA.

The feasibility study establishes objectives for the project and evaluation criteria to assess different options. The study concluded the preferred option that best achieves the project objectives related to public safety, environmental impacts and trail connectivity is to decommission the dam.

The final layout and amenities will be explored through detailed design and permitting in consultation with the public, the Town of Mono and stakeholders. Based on the preferred option under consideration, the site will have a natural cascading stream, with park elements and nature designed to function with the surroundings and park use. The river channel will be restored, and some wetlands will be established within the existing pond basin. Initially, there may be some exposed muddy areas, but they will quickly grow vegetative cover and will be planted with trees and shrubs.

Upcoming Events

Restoration News

Credit Valley Conservation (CVC) is continuing its efforts to bring back healthy forests to Rattray Marsh Conservation Area …

Monora Park Dam Mitigation Continue Reading

Credit Valley Conservation (CVC) invites residents to learn about the pond and dam removal at Monora Park at …

Monora Park Dam Mitigation Continue Reading

May 26, 2022 – Credit Valley Conservation (CVC) has begun lowering water levels in Monora Pond to restore …

Monora Park Dam Mitigation Continue Reading

Scroll to Top