2021 Permit Fees
Ontario Regulation 160/06 Permit Applications | Permit Fees |
Development – Small Scale | $450 |
Development – Medium Scale | $1,350 |
Development – Large Scale | $3,250 |
Development – Major Scale | $5,500 |
Interference with Wetlands and Alterations to Watercourses and Shorelines – Small Scale | $800 |
Interference with Wetlands and Alterations to Watercourses and Shorelines – Medium Scale | $2,250 |
Interference with Wetlands and Alterations to Watercourses and Shorelines – Large Scale | $6,500 |
Interference with Wetlands and Alterations to Watercourses and Shorelines – Major Scale | $11,000 |
Permit for Minor Works | $150 |
Permit Revisions/Review of Repeat Submissions | Small scale: 25% of current fee Others: 50% of current fee |
Expedited Review (Director approved – subject to resources available) | Additional 100% of current fee |
In Stream Timing Window Extension | Minor $500 Major $5000 |
Fill Placement (less than 500m3)* Large Fill Placement (greater than 500m3)* |
$400 $10,000 plus $1.00 per m3 |
Additional Site Visit | $200 |
Property Information | Fee |
Solicitor/Realtor/Property Inquiry | $325** |
GIS Information Request/Service | $50-$75/hr+HST |
*500m3 is equivalent to approximately 50 truckloads.
**HST applicable to Solicitor/Realtor/Property Inquiry only. The $325 fee includes the HST.
Notes
- The application fee must be paid at the time of filing an application. A permit will not be issued unless the application fee has been submitted.
- CVC reserves the right to modify or adjust fees should the review require a substantially greater or lower level of review and/or assessment.
- Fees related to review of repeat submissions (more than 3 submissions) will be determined by CVC depending on the number, completeness and quality of the repeat submissions.
- All permits are issued for two years. Permit extensions and/or renewals will not be granted. However, applicants may re-apply for re-issuance of a new permit for the original approved works in accordance with the most recent technical requirements.
- For Permits associated with “Unauthorized Works” or a “Violation”, the fee will be double the applicable application fee.
- For large fill placements, the CVC Procedural Guideline for receiving and processing applications to place fill in excess of 500 cubic metres should be referenced.
Definitions
- Small Scale: an application is determined to be “Small Scale” where no technical studies are required.
- Medium Scale: an application is determined to be “Medium Scale” where limited or scoped technical studies are required.
- Large Scale: an application is determined to be “Large Scale” where technical studies are required.
- Major Scale: an application is determined to be “Major Scale” where a number of technical studies are required (hydraulic analysis, storm water management, geotechnical, etc.).
- Minor in the In Stream Timing Window Extension is applicable where the request to extend the timing window is made well in advance of the final date, is considered low risk and requires minimal review.
- Major in the In Stream Timing Window Extension is applicable where the request to extend the timing window is made within less than a week of the final date and/or requires considerable review and effort by CVC staff.